(Legion Street still a High Priority Project)…Legion Street is in Brawley.
The City has prioritized Legion Street from Highway 86 to western City limits for improvement. The overall project is estimated at $2 million and will be primarily paid for with State and Federal funds that flow through the Imperial County Transportation Commission. Local funds are being applied for a match that hovers around 11.5%. The Legion Street Project will be addressed in 3 phases. Phase one extends from Highway 86 to Evelyn Avenue. Phase two will be from Evelyn to Kelley Avenue. Phase 3 will be from Kelley to the Westerly City Limits. The 3 phases are expected to be complete by June 30th, 2021.