The City of El Centro has issued an update on the La Brucherie Avenue widening project.

According to the city , the major underground work has been completed and the majority of the sidewalks and driveways have been installed. The new roadway subgrade is also nearly prepared with base replacement to start this week and paving scheduled to begin May 6. Striping of the roadway will take place about a week after paving. New street lights  and signal poles will also be installed. If all work stays on schedule , substantial completion of the project is expected by Friday , May 17, 2019.